STRANGERS CREEK REHABILITATION

1/6
LOCATION | KELLYVILLE NSW
 
CLIENT | ST HILLIERS

​THE BRIEF

 

Terra Civil was contracted to realign the Strangers Creek trunk drainage corridor, rehabilitate the creek and improve its environmental & aesthetic appeal.   

 

THE CHALLENGE

 

Studies of the Strangers Creek environment established that the creek was no longer meeting its original purpose as a trunk drainage waterway designed to protect both public health and the environment. 

 

THE PROJECT

 

Working around a variety of environmental challenges including those imposed by continual water flow Terra Civil’s first priority was to stabilise the banks. 

 

With ecological considerations - including the preservation of natural flora and fauna and the maintenance of a healthy ecological environment - a priority, Terra Civil worked in close collaboration with a team of Environmentalists to deliver the project. 

 

Meeting the projects 12-month deadline, Terra Civil realigned the trunk drainage corridor and rehabilitated the creek, creating significant environmental improvements while at the same time demonstrating the social and aesthetic benefits of sound river management and biodiversity projects.

 

KEY DELIVERABLES 

  • Demolition works 

  • Asbestos removal and remediation

  • 1.9 km of creek rehabilitation

  • 200,000m2 of vegetation removal

  • Removal of 200 trees

  • 10,000t of acid sulphate soil treatment and removal

  • Import 11,000t shale

  • Place, trim and compact shale to reshape creek bed

  • Cut and shape creek batters 8,500m3

  • Supply and place 6,500 sandstone armour rock to create ripple batters in the creek bed and natural ponds

  • Supply and construct 786LM of sandstone log retaining walls using approximately 2000 2m x 500 sandstone logs

  • Supply, trim and spread soil (15,000 m2)

  • Removal of 15000 ton of VENM material

 

SERVICES

 

Remediation Works

Detailed Excavation